BuiltSum

What is AIA billing?

By BuiltSum · Published · Updated

AIA billing is progress billing using the American Institute of Architects’ standardized pay-application format: the G702® Application and Certificate for Payment, which summarizes the contract sum, work completed, retainage, and the payment currently due, and the G703® Continuation Sheet, which breaks the contract into a schedule of values billed line by line. Contractors submit the package monthly; the architect or owner’s representative certifies it; payment follows the certified amount.

  1. 1 · Before App #1

    Schedule of values

    Original contract
    $248,500
    + CO-01
    $6,200
    C — scheduled values
    $254,700

    Approved once. The lines must sum to the contract sum to date, to the cent.

  2. 2 · Every line, every month

    G703-style continuation sheet

    D — previous applications
    $78,230
    E — this period
    $68,240
    F — materials stored
    $20,100
    G = D + E + F
    $166,570

    Percent complete is G ÷ C; balance to finish is C − G; retainage is figured on G.

  3. 3 · One page, nine lines

    G702-style summary

    Line 4 — completed & stored
    $166,570
    Line 5 — retainage (10%)
    −$16,657
    Line 6 — earned less retainage
    $149,913
    Line 7 — previous certificates
    −$70,407
    Line 8 — current payment due
    $79,506

    Line 4 is the continuation sheet's column G total, never a separate number.

  4. 4 · By the contract cutoff

    Certification & payment

    Contractor signs
    (notarized if required)
    Architect certifies
    ≤ $79,506
    Owner pays
    certified amount

    The architect can certify less than requested if they dispute progress on a line.

Next month: this period’s certified figures become App #4’s column D (previous applications) and line 7 (previous certificates). If either is retyped instead of rolled forward, the totals stop matching and the pay app bounces.

One billing period, end to end, using the sample pay application below (App #3 on a $254,700 contract, 10% retainage).

Why GCs require it

On commercial work, the general contractor bills the owner once a month and needs every subcontractor’s billing in a format that rolls up cleanly. The AIA format has been the de facto standard for decades: the same nine summary lines, the same continuation-sheet columns, the same retainage arithmetic — so an architect can certify twenty pay apps without decoding twenty invoice styles.

The G702-style summary, line by line

  1. Original contract sum — the value of the signed contract.
  2. Net change by change orders — approved additions minus deductions to date.
  3. Contract sum to date — line 1 + line 2.
  4. Total completed and stored to date — the continuation sheet’s total: all work performed plus materials stored on site, from job start through this period.
  5. Retainage — the percentage withheld, usually split between completed work (5a) and stored materials (5b).
  6. Total earned less retainage — line 4 − line 5.
  7. Less previous certificates for payment — everything already certified on earlier applications.
  8. Current payment due — line 6 − line 7. The number everyone reads first.
  9. Balance to finish, including retainage — line 3 − line 6.

The G703-style continuation sheet

Each schedule-of-values line carries its scheduled value, work completed in previous periods, work completed this period, materials presently stored, the total completed and stored, percent complete, balance to finish, and retainage. Two rules keep it acceptable: the scheduled values must sum exactly to the contract sum to date, and the “previous applications” column must match what was certified last month. When either drifts — usually after a change order or a hand-typed roll-forward — the pay app bounces.

BuiltSum pay application generator showing a seven-line G703-style continuation sheet with previous, this period, stored materials and retainage columns, and a current payment due of $79,506
Application #3 on a sample $254,700 interiors contract: each line rolls previous work forward, adds this period and stored materials, and the G702-style totals fall out of the continuation sheet. Open the pay application generator →

Official forms vs. “AIA-style”

G702 and G703 are copyrighted; official copies are licensed through AIA Contract Documents (single-use from about $49.99, or roughly $2,199.99/user/year for a subscription). That is why billing software produces AIA-style documents — independently designed forms presenting the same functional information. Most GCs accept them; a minority of contracts require official forms, so check yours. BuiltSum is not affiliated with the AIA, and its documents are AIA-style, not official AIA Contract Documents.

Is an “AIA invoice” the same thing?

Yes. Contractors say AIA invoice, AIA pay app, AIA billing formand application for payment interchangeably. They all mean the G702-style summary plus the G703-style continuation sheet submitted for one billing period. The difference from an ordinary invoice is structural: an AIA-style invoice bills a portion of a fixed contract against an approved schedule of values, subtracts what was already certified, and withholds retainage, so the amount due is derived rather than typed. If a GC asks for an “AIA invoice template”, the free pay application generator produces exactly that document, and straight invoicing covers the small jobs that never need one.

Billing for stored materials

Column F of the G703-style sheet, Materials Presently Stored, lets you bill for material that is delivered and paid for but not yet installed, which matters on jobs with long-lead items such as switchgear, stone or custom millwork. Three rules keep it from being rejected: the contract has to allow it (many AIA A201-based contracts do, some GCs strike it), the material must be on site or in a bonded, insured off-site store with the owner named, and you attach invoices plus a stored-materials log so the reviewer can tie the value to something physical. Once installed, the amount moves out of column F and into work completed, so the same dollars are never counted twice, and retainage may apply at a different rate to stored materials than to completed work, which is why a pay app should track the two separately.

Why pay applications get sent back

A returned application usually costs a full billing cycle, because the corrected version misses the cut-off and waits for next month. The reasons repeat:

  • It doesn’t tie to the last certificate. Line 7 (previous certificates) must equal what was actually certified last period, not what you billed. If the architect cut your last application, this period starts from the cut number.
  • Unapproved change orders on the sheet. Pending changes belong on a separate log until they are signed. Billing them early gets the whole application rejected, not just the line.
  • Percent complete the reviewer can’t see. A line claiming 80% on a floor that looks half done invites a cut across every line. Bill what is in place.
  • Retainage at the wrong rate or on the wrong base. Common after a 50% step-down, or when stored materials carry a different rate than completed work.
  • Missing backup. Conditional lien waivers for this period, unconditional waivers for the last one, certified payroll on prevailing-wage work, and invoices for stored materials. Most GCs list their required attachments in the subcontract; check it once and build a checklist.
  • Rounding. Totals computed on the summary instead of rounded per line come out a few cents different from the continuation sheet, and the reviewer cannot certify a number that does not foot.

AIA billing vs. other ways to bill a job

MethodWhat you billTypical use
AIA-style progress billingPercent complete per schedule-of-values line, less retainage and prior certificatesCommercial and public work with a GC or architect certifying each month
Lump-sum invoiceThe agreed price, once or in a few fixed depositsSmall residential and service jobs
Milestone billingFixed amounts when defined stages are reachedResidential builds and remodels with a draw schedule
Time and materialsHours at agreed rates plus materials with markupRepair, emergency and undefined-scope work
Unit priceMeasured quantities times contract unit ratesCivil, paving and utility work

The methods mix. A unit-price contract can still be billed on a G702/G703-style application, with the continuation sheet listing quantities instead of percentages, and change orders on an AIA job are often priced as time and materials before they are added to the schedule of values as new lines.

Doing it without retyping every month

The painful part of AIA billing is not the first application — it’s the tenth: rolling every line’s totals forward, keeping retainage consistent, folding in change orders, and reconciling previous certificates. You can do it free with our pay application generator (it saves your schedule of values and rolls it forward), check withholding against your state’s cap with the retainage calculator, or let BuiltSum run the whole chain from estimate to certified payment.

Frequently asked questions

What does AIA stand for in AIA billing?

AIA is the American Institute of Architects, the body that publishes the G702 Application and Certificate for Payment and the G703 Continuation Sheet. 'AIA billing' means progress billing submitted in that two-form format, whether on the licensed originals or an AIA-style equivalent. The architect's involvement is not incidental: the format exists so the architect can certify how much work is complete before the owner pays.

Do I have to buy official AIA forms?

Only if your contract says so. Official G702/G703 forms are licensed at aiacontracts.com — single-use documents start around $49.99 and a full AIA Contract Documents subscription runs roughly $2,199.99 per user per year. That cost is why virtually all construction billing software (Werx, Knowify, BuiltSum) produces 'AIA-style' documents instead: original layouts carrying the same information, accepted by most GCs.

Who signs a G702-style application?

The contractor signs a certification that the work billed was performed under the contract; many owners require notarization. The architect (or owner's representative) then signs a certificate approving payment of the certified amount — which can be less than the amount requested if they dispute progress.

How often is AIA billing submitted?

Monthly, on the schedule fixed in the contract — commonly by the 20th or 25th so the GC can roll sub pay apps into its own application to the owner. Miss the cutoff and your payment typically slips a full month.

What is an AIA invoice?

An AIA invoice is the everyday name for an AIA-style application for payment: the G702-style summary and G703-style continuation sheet a contractor submits for one billing period. It differs from a normal invoice because it bills a portion of a fixed contract against a schedule of values, subtracts prior certificates and withholds retainage, so the amount due is calculated rather than typed.

Can I bill for stored materials on an AIA pay app?

Usually, if the contract allows it. Delivered-but-uninstalled material goes in the Materials Presently Stored column with backup invoices and a stored-materials log; once installed it moves into work completed so it is never counted twice. Some contracts apply a different retainage rate to stored materials, so track them separately.

What happens if my pay app has a math error?

The GC or architect rejects it, and the correction cycle usually costs you the billing period — 30 more days of financing the work. The most common errors are retainage drift across periods, continuation-sheet lines that stop summing to the contract sum after a change order, and previous-application columns that don't match last month's certified totals.

Can QuickBooks do AIA billing?

Partly. QuickBooks Online and Desktop do progress invoicing against an estimate, and since 2026 QuickBooks Online Advanced adds AIA-style invoicing by project phase. Intuit's documentation does not describe a G702-style summary, a G703-style continuation sheet, retainage or previous-certificate roll-forward, so contractors whose GC requires the full application still build it elsewhere and post the certified amount to QuickBooks as an invoice, which is what BuiltSum's QuickBooks Online sync does.

What is the AIA billing format?

Two documents. The G702-style summary carries the contract in nine lines: original contract sum, net change orders, contract sum to date, total completed and stored to date, retainage, total earned less retainage, less previous certificates for payment, current payment due, and balance to finish. The G703-style continuation sheet lists every schedule-of-values line with scheduled value, work from previous applications, work this period, materials presently stored, total completed and stored, percent complete, balance to finish and retainage. The continuation sheet totals feed the summary.

How do you use AIA billing, step by step?

Get the schedule of values approved before the first application. Each period, enter work completed and stored materials per line; retainage and the nine summary lines calculate from those. Sign the contractor's certification (notarize it if the contract requires), attach backup such as lien waivers and stored-material invoices, and submit by the contract's cutoff date. The architect or owner's representative certifies an amount, which may be less than requested. Next period, the certified figures become the 'previous applications' column, so the two must match exactly.

AIA-style billing without the spreadsheet

Unlimited projects, per-line retainage, roll-forward periods — from $49/mo.

Start free