Retainage Calculator

Retainage is the portion of each construction progress payment — typically 5–10% — that the owner or GC withholds until the work is complete. This free calculator shows how much is being withheld on your job, what is payable to date, and whether your rate exceeds your state’s statutory cap.

Tip: every field takes math — type 125000+80000 or 3200*40 and we’ll do the arithmetic.

Earned to date
$150,000.00
Retainage withheld to date
$15,000.00
Net payable to date
$135,000.00
Total retainage at completion
$25,000.00

Federal (FAR)public projects: No automatic retainage: CO may retain up to 10% of a progress payment ONLY if satisfactory progress not achieved; else pay in full (FAR 52.232-5(e))

Educational estimate only — retainage statutes change and contracts vary. Verify against your contract and current state law. This is not legal advice.

Retainage laws by state (2026)

Statutory caps on retainage for public and private construction projects. “No cap” means the state has no statute limiting the rate — your contract governs. Last reviewed 2026-08-14. Laws change; verify before relying on a row.

JurisdictionPublic capPublic rulePrivate capCitation
Federal (FAR)10%No automatic retainage: CO may retain up to 10% of a progress payment ONLY if satisfactory progress not achieved; else pay in fullNo capFAR 52.232-5(e)
Alabama5%5% cap on state public works; no further retainage after 50% completion; final payment within 35 days of completion/acceptance10%Ala. Code § 39-2-12(c); § 8-29-3(i)
AlaskaNo capNo statutory cap; set by contract. Subs paid retainage within 8 working days of prime's final payment or 90 days after last workNo capAS §§ 36.90.210, 36.90.250 (public timing only)
Arizona10%10% cap; half of withheld retainage released at 50% completion (5% thereafter if satisfactory); release within 60 days of completionNo capA.R.S. § 34-221(C); § 32-1182(D)
Arkansas5%5% cap per progress payment; withholding may cease at 50% completion with satisfactory progress; release within 30 days of completionNo capArk. Code Ann. § 22-9-604
California5%5% cap per payment and of total price; exception if pre-bid 'substantially complex' finding; release within 60 days of completion5%Cal. Pub. Cont. Code § 7201; Civ. Code §§ 8811–8812
Colorado5%5% cap (entity must pay at least 95% of completed work value); final settlement within 60 days of completion and acceptance5%C.R.S. § 24-91-103; § 38-46-103
Connecticut7.5%State projects 7.5%, reduced to 5% at 50% completion; municipal projects 5%; DOT projects 2.5%5%Conn. Gen. Stat. § 49-41b; § 42-158k
Delaware5%5% cap; 60% of retainage releasable at completion; release within 60 days of completion, then max 150% of expected remaining costsNo cap29 Del. C. §§ 6516(3), 6962(d)(5)
District of Columbia10%10% withheld until completion and acceptance; Mayor may reduce at 50% completion (prime–District contracts only)No capD.C. Code § 2-203.01
Florida5%5% cap per progress payment (former 10/5 step-down eliminated); release within 30 days after substantial completionNo capFla. Stat. §§ 255.078, 255.077; § 715.12
Georgia10%10% per progress payment; no further retainage after 50% completion if progress satisfactory; release within 30 days of substantial completionNo capO.C.G.A. §§ 13-10-80; 13-11-5
Hawaii5%Max 5% of amount due; after 50% completion with satisfactory progress no additional sums withheld; bonded subs get same rateNo capHaw. Rev. Stat. §§ 103-32.1, 103-32.2
Idaho5%5% cap on bonded public work; release within 30 days after acceptance of completed portions; GC remits to subs within 30 days5%Idaho Code §§ 54-1926; 29-115
IllinoisNo capNo general statutory cap on public projects; contract terms govern (separate prompt-pay timing for highway work)10%815 ILCS 603/20; 605 ILCS 5/4-103
Indiana10%Local >$200k: 6–10% until 50% complete, none after; state contracts: 6% to 50% or 3% to substantial completion; release in 61 daysNo capInd. Code §§ 36-1-12-14; 4-13.6-7-3
Iowa5%Max 5% of amount due; no step-down; release within 30 days of completion and final acceptance; early-release option at 95% completeNo capIowa Code §§ 573.12–573.15A
Kansas10%5% default; up to 10% only if needed to ensure performance; release within 30 days after substantial completion (10% road/bridge cap)10%K.S.A. 16-1904; 16-1804; 68-411
Kentucky10%10% of undisputed payments until 50% complete, then max 5% of total contract; release within 30 days of substantial completion10%Ky. Rev. Stat. § 371.410
Louisiana10%10% on projects under $500k; 5% on projects $500k and over; may be withheld up to 45 days after formal completion and acceptanceNo capLa. R.S. 38:2248; 9:4815
Maine5%5% withheld on state contracts; may be reduced upon substantial completion; released when work accepted by or for the StateNo cap5 M.R.S. § 1746; 10 M.R.S. § 1116
Maryland5%Max 5% when 100% payment/performance security posted; release within 120 days of satisfactory completion; subs capped at same rate5%Md. Code, State Fin. & Proc. § 17-110; Real Prop. § 9-304
Massachusetts5%Max 5% of each periodic payment; release within 65 days of substantial completion; ~1% may be held pending final completion5%Mass. Gen. Laws ch. 30 § 39K; ch. 149 § 29F
Michigan10%Max 10% until work 50% in place, then no further retainage if progress satisfactory; funds escrowed interest-bearingNo capMich. Comp. Laws § 125.1563
Minnesota5%Max 5% of progress payments; agency may reduce/eliminate; release within 60 days of substantial completion (250% punch-list holdback allowed)5%Minn. Stat. §§ 15.71–15.74; § 337.10 subd. 4
Mississippi5%5% on state contracts (county 2.5–10% by size); contracts >$250k drop to 2.5% after 50% complete with half of held retainage returnedNo capMiss. Code Ann. §§ 31-5-33, 31-5-15, 19-13-15
Missouri5%Max 5% (10% only if unbonded contract under $50k); release with final payment, may hold 150% of punch-list value10%Mo. Rev. Stat. § 34.057; §§ 436.303, 436.324
Montana5%Max 5% if contractor performing per contract; final payment within 30 days of final acceptance; subs capped at rate withheld from GC5%Mont. Code Ann. § 18-2-316; §§ 28-2-2107, 28-2-2110
NebraskaNo capNo statutory retainage cap for public projects; set by contract10%Neb. Rev. Stat. § 45-1204
Nevada5%5% withheld until 50% of work done; then max 2.5% on later payments and half of held retainage repaid; release ~30 days after occupancy5%Nev. Rev. Stat. §§ 338.515, 338.555; §§ 624.609, 624.624
New HampshireNo capRetainage permitted but no statutory rate; state contracts >$500k may substitute securities for retained fundsNo capN.H. Rev. Stat. Ann. § 21-I:20
New Jersey2%2% cap on local/state contracts >$100k; drops to 1% at substantial completion; school boards up to 5% (2% w/ bond); release in 45 daysNo capN.J.S.A. 40A:11-16.3; 27:7-34; 18A:18A-40.3
New MexicoProhibitedRetainage prohibited (Retainage Act); narrow exception: up to 5% on road/highway projects under NMSA 67-3-48ProhibitedNMSA § 57-28-5; § 67-3-48
New York5%5% cap (10% if no payment/performance bond); release ~30 days after approval; subs paid within 7 days5%State Fin. Law § 139-f; Gen. Mun. Law § 106-b; Gen. Bus. Law § 756-c
North Carolina5%5% on projects ≥$100k until 50% complete, then no further retainage if work satisfactory; early-finish trades reduced to 0.5%No capN.C. Gen. Stat. § 143-134.1
North Dakota10%10% of each estimate until 50% complete, then no further retainage; 95% of retained funds released at 95% completion10%N.D.C.C. §§ 40-22-37; 43-07-23
Ohio8%8% of each payment until 50% complete, then no further retainage; escrow required; release ~30 days after acceptanceNo capOhio Rev. Code §§ 153.12, 153.13, 153.63
Oklahoma5%5% cap on public payments; release within 21 days of substantial completion (less up to 150% of correction costs)No capOkla. Stat. tit. 61, § 226
Oregon5%5% cap; may reduce after 50% complete with surety approval; interest-bearing escrow required over $500k; 1.5%/mo late interest5%ORS 279C.570; ORS 701.420
Pennsylvania10%10% cap; at 50% completion half of retainage returned and max drops to 5%; DGS 6%/3%; highways 5% with none after 50%No cap62 Pa.C.S. § 3921; 73 P.S. § 509
Rhode Island5%5% cap on state/municipal works; release within 90 days of acceptance or 10%/yr interest; RIDOT exempt but still limited to 5%5%R.I. Gen. Laws §§ 37-12-10; 37-12-10.1
South Carolina3.5%Max 3.5% of each progress payment; retainage on a completed division of work released within 10 days of certificationNo capS.C. Code Ann. § 11-35-3030(4)
South DakotaNo capNo cap: statute sets a MINIMUM sliding scale on county work (12% first $50k, 5% next $200k, 2.5% above); interest accrues 60 days after completionNo capS.D. Codified Laws § 7-25-10
Tennessee5%Max 5%; escrow in interest-bearing account required if contract ≥$500k; release within 90 days of (substantial) completion5%Tenn. Code Ann. §§ 66-34-103, 66-34-104
Texas10%Max 10% if contract <$5M; max 5% if ≥$5M; interest-bearing account if retainage >5%No capTex. Gov't Code § 2252.032; Tex. Prop. Code §§ 53.101–53.105
Utah5%Max 5% of total construction price; release within 45 days of billing/final acceptance or certificate of occupancy5%Utah Code Ann. § 13-8-5
VermontNo capNo statutory cap; retained amounts due on final completion must be paid within 30 days after final acceptanceNo capVt. Stat. Ann. tit. 9, § 4005
Virginia5%Max 5% of each progress payment (contractor paid at least 95% of earned sum); release via prompt-pay rulesNo capVa. Code Ann. §§ 2.2-4333, 2.2-4334
Washington5%Max 5% (10% allowed in lieu of bond on contracts ≤$150k); release within 60 days of completion (30 days for the 10% option)5%RCW 60.28.011; RCW ch. 60.30 (SB 5528, 2023)
West VirginiaNo capNo retainage statute for public projects — amount, timing, and release are set entirely by contractNo cap
Wisconsin5%State projects: max 5% until 50% complete, then none if progress satisfactory (up to 10% if not); paid at substantial completionNo capWis. Stat. § 16.855(19)
Wyoming5%Max 5% on public works; after 50% completion with satisfactory progress, entity may release withheld amounts on written requestNo capWyo. Stat. Ann. §§ 16-6-702(b), 16-6-704

Billing AIA-style pay apps with retainage every month? The free pay application generator carries retainage line-by-line and rolls your schedule of values forward each period. Read more in What is retainage in construction?

Frequently asked questions

How is retainage calculated?

Retainage = work completed to date × the retainage rate in your contract. On a $250,000 contract that is 60% complete with 10% retainage, $150,000 has been earned and $15,000 is withheld, so $135,000 is payable to date. Retainage is typically withheld from every progress payment and released at substantial completion or final acceptance.

What is a typical retainage percentage?

5% to 10% is standard. Federal projects allow up to 10% only when the contracting officer finds satisfactory progress lacking (FAR 52.232-5). Many states cap public-project retainage at 5%, and a growing number cap private retainage too — check the table on this page.

When must retainage be released?

It depends on the contract and jurisdiction. Common triggers are substantial completion, final acceptance, or a statutory deadline after completion. Several states require retainage to step down (for example, reduce by half once the project passes 50% completion). Track release milestones — unreleased retainage is one of the most common ways subcontractors silently lose margin.

Does retainage apply to change orders?

Usually yes. Approved change orders increase the contract sum, and retainage is withheld on the revised total unless your contract says otherwise. Make sure your schedule of values and pay applications carry change orders through, or your retainage math will drift from the GC's.