Construction estimate template, as an interactive builder
A construction estimate template should do the math, not just hold the numbers. This free builder starts from ten trade packs (painting, drywall, concrete, masonry, excavation, landscaping, siding, framing, tile, insulation) — material and labor per unit already loaded — applies your labor rate, burden, and markup, and produces a signature-ready proposal PDF. Every numeric field accepts math like 12*14+9*11.
Interior — walls & ceilings
Interior — trim & doors
Interior — cabinets
Exterior
Prep add-ons
Pack v2026.08: starting defaults for a mid-market US crew — edit any unit cost or production rate below to your numbers. Save estimates to your account and these become your own price book.
| Description | Qty | Unit | Mat $/unit | Labor hr/unit | Material | Labor | Price |
|---|
- Material
- $0.00
- Labor hours
- 0
- Labor (burdened)
- $0.00
- Cost
- $0.00
- Markup
- $0.00
- Bid price
- $0.00
The chain: this estimate → schedule of values → monthly AIA-style pay applications. All free, and saved in your browser until you put it in an account.
How to fill in the estimate template
- Quantities first, prices second. Measure from the drawings (the free browser takeoff sends quantities straight in) and enter them per assembly. A price on a guessed quantity is still a guess.
- Use assemblies, not bare unit prices. An assembly carries material and labor per unit, so “120 SF of level 4 drywall” prices the board, mud, tape and the hours together. Adjust the production rate if your crew is faster or slower than the default rather than fudging the unit price.
- Put the real labor cost in, burdened. The wage is not the cost. Run your rate through the labor burden calculator first; a $30 wage is usually a $40 to $45 hour once taxes, comp and unbillable time are paid for.
- Markup is not margin. The template applies markup on top of cost. If your target is a 20% margin on price, that is a 25% markup; the markup calculator does the conversion. Add contingency as its own line, visible to you and hidden from the client.
- Export the proposal from the same numbers. The PDF is built from the estimate, so a change to a quantity changes the proposal. Once accepted, the lines become the schedule of values you bill against.
Frequently asked questions
What should a construction estimate include?
A scope of work broken into line items with quantities and units, material and labor for each, your labor burden (payroll taxes, workers' comp, insurance — typically 20–35% on top of wages), overhead-and-profit markup, any tax, and the total. A client-facing proposal shows scope and prices; the cost columns stay internal.
Why use this instead of an Excel estimate template?
A spreadsheet template starts you from a blank page on every bid, and formulas drift as you copy jobs. This builder starts from trade assemblies — line items with material cost and production-rate labor already baked in — so you type quantities, not formulas. Every field also accepts math (330+275+113), and the output is a clean proposal PDF, not a screenshot of a grid.
What's the difference between markup and margin?
Markup is a percentage added to cost (30% markup on a $10,000 cost = $13,000 price). Margin is profit as a share of price ($3,000 of $13,000 ≈ 23% margin). Contractors quoting '30 percent' often mix these up and underprice; this builder applies markup on cost, and you can see the resulting dollars before you send.
Where do the default prices come from?
They are BuiltSum-authored starting values for a mid-market US crew — not licensed cost-book data, and deliberately editable. The whole point is to reprice them from your own jobs: your labor rate, your suppliers, your production rates. Price off your history, not a stale book.
Win the bid, then bill it
In BuiltSum, this estimate becomes your schedule of values and monthly AIA-style pay applications — entered once.